Key Dates of the Installation Programme
All dates are provisional as at 13 March
| 24 March 2003 | Enter Albion Dry Dock |
| 28 March | Create access by removing funnel casing and part of promenade deck |
| 4 April | Renew upper cowl of funnel |
| 8 April | Removal of Newbury Sirron engines |
| 14 April | Refitting of funnel casing (the new engines are smaller and will require smaller access) |
| 18 April | Installation of gearboxes |
| 5 May | Undocking |
| 9 May | Installation of Grenaa engines |
| 13 May | Refitting of Promenade Deck |
| 20 May | Sea trials |
| 22 May | Vessel due Glasgow |